As of 1:30 this afternoon RELAC started producing chilled water.  It will take a couple of hours for the total system to cool down.  We missed the by noon of the 2nd consecutive 80 degree day by a few hours.


Mike and Lamont worked with RA to install a tennis net across the opening by the  pump house.  By adding floats and weight to the tennis net they were able to keep it in the correct place.   Hopefully this will catch enough debris for operations.   If too much debris gets into the plant it can clog the screens and filters and shutdown the chillers.


At a later date the net will be replaced with the proper type of net.