February 22, 2018

20018.04 / Lake Anne West
·         WSSI to order and post “No Mowing” signs
·         Bollard to be installed by TDS to block vehicular traffic at LAW-01 bridge
·         Tentative schedule for completion by the end of February:
Friday
2/23/2018
Upper bridge (LAW-01) railings installed
Thursday
2/22/2018
Plants delivered – planting to start next week
Monday
2/26/2018
Paving starts*
Wednesday
2/28/2018
Gravel shoulder installed along path
*Final asphalt when daytime temps stay above 45° F and weather is dry, towards
Beginning of next week.  Paving will be accessed from upstream at Bachan Ct.

February 15, 2018

Below are the meeting notes and the updated tentative completion schedule.

TDS crews will not be working next Monday, President’s Day.

20018.04 / Lake Anne West
·         WSSI to order and post “No Mowing” signs
·         Possible bollard installation discussed to inhibit vehicle traffic
·         Tentative schedule for completion by the end of February:
Thursday
2/15/2018
Lower bridge railings installed
Thursday
2/15/2018
Construction entrance removal
Friday
2/16/2018
Upper bridge footers set
Tuesday
2/19/2018
Upper bridge deck set and railings started
Thursday
2/22/2018
Paving*
Thursday
2/22/2018
Plants arriving
*Final asphalt when daytime temps stay above 45° F, towards
end of next week. Paving will be accessed from upstream Bachan Ct.

Let us know if you have any questions.

Daniel Misch |Ecosystem Specialist
ISA Certified Arborist UT-4564AU

February 10, 2018

Lake Anne West 2/7/2018
·         Sub-surface flow is expected in low flow conditions until voids are filled
·         Bridge piers installed for downstream bridge (LAW-02) Tuesday 2/6/18
·         Oak tree at tributary 2 made safe with crown removal completed Tuesday 2/6/18
·         TDS punch list items
o   Stabilize around upstream headwall STA 10+00.00 with A1 Rip Rap
o   Cut white pipe back to bank
o   Install pipes under trail at Tributary 1
·         TCOT planting access with gator/cart
·         Tentative schedule for completion by the end of February:
Thursday
2/8/2018
Lower pedestrian bridge (LAW-02) installation
Friday
2/9/2018
Construction entrance removal
Monday
2/12/2018
Upper pedestrian bridge (LAW-02) installation
Thursday
2/15/2018
Paving*
Monday
2/19/2018
Planting
*Final asphalt when daytime temps stay above 45° F, towards
end of next week. Paving will be accessed from upstream Bachan Ct.