Maintaining current contact information helps the board and its committees reach owners and tenants with important board announcements as well as during emergency events such as a water/gas main break or to report storm damage to vehicles or other property.  Each owner and paying tenant should complete a separate form.  Non-resident owners should enter their address at the end of the form.  Note: You do NOT need to have a Google account in order to update and submit the form.

February 28, 2018

20018.04 / Lake Anne West
·         Next Wednesday 3/7/18 will be the final meeting and walk through for Lake Anne West
·         WSSI will post “No Mowing” signs Thursday 3/1/18
·         WSSI will closely monitor for any potential erosion on slope near construction entrance per resident request
·         WSSI to follow up with Waterview cluster on when vehicles can be driven down path
o   Waterview cluster to determine what equipment will be used for landscaping
·         TCOT will finish planting Thursday 3/1/18
·         TDS will replace concrete Thursday 3/1/18 weather permitting
o   @ Construction entrance
§  All panels impacted by construction
o   @ Junction of Bachan Ct. & trail
§  3 panels nearest trail
§  Apron around drop inlet
·         TDS will complete trail shoulders and the following action items early next week
o   @ Construction entrance
§  Install bollard
§  Cut 4’ holly stump closer to grade
o   @ Junction of Bachan Ct. & trail
§  Replace timber and river cobble at corner of trail
§  Replace wooden post for guard rail
o   Near lower trail crossing at bridge LAW-02
§  Remove cable from Ash Log
§  Replace timber in landscaping on south side of trail
§  Re-grade minor erosion in last stream access point

February 25, 2018

The WVC BoD will meet Monday, March 5, at 7:00 PM at 11463 Waterview.

February 22, 2018

20018.04 / Lake Anne West
·         WSSI to order and post “No Mowing” signs
·         Bollard to be installed by TDS to block vehicular traffic at LAW-01 bridge
·         Tentative schedule for completion by the end of February:
Friday
2/23/2018
Upper bridge (LAW-01) railings installed
Thursday
2/22/2018
Plants delivered – planting to start next week
Monday
2/26/2018
Paving starts*
Wednesday
2/28/2018
Gravel shoulder installed along path
*Final asphalt when daytime temps stay above 45° F and weather is dry, towards
Beginning of next week.  Paving will be accessed from upstream at Bachan Ct.

February 15, 2018

Below are the meeting notes and the updated tentative completion schedule.

TDS crews will not be working next Monday, President’s Day.

20018.04 / Lake Anne West
·         WSSI to order and post “No Mowing” signs
·         Possible bollard installation discussed to inhibit vehicle traffic
·         Tentative schedule for completion by the end of February:
Thursday
2/15/2018
Lower bridge railings installed
Thursday
2/15/2018
Construction entrance removal
Friday
2/16/2018
Upper bridge footers set
Tuesday
2/19/2018
Upper bridge deck set and railings started
Thursday
2/22/2018
Paving*
Thursday
2/22/2018
Plants arriving
*Final asphalt when daytime temps stay above 45° F, towards
end of next week. Paving will be accessed from upstream Bachan Ct.

Let us know if you have any questions.

Daniel Misch |Ecosystem Specialist
ISA Certified Arborist UT-4564AU

February 10, 2018

Lake Anne West 2/7/2018
·         Sub-surface flow is expected in low flow conditions until voids are filled
·         Bridge piers installed for downstream bridge (LAW-02) Tuesday 2/6/18
·         Oak tree at tributary 2 made safe with crown removal completed Tuesday 2/6/18
·         TDS punch list items
o   Stabilize around upstream headwall STA 10+00.00 with A1 Rip Rap
o   Cut white pipe back to bank
o   Install pipes under trail at Tributary 1
·         TCOT planting access with gator/cart
·         Tentative schedule for completion by the end of February:
Thursday
2/8/2018
Lower pedestrian bridge (LAW-02) installation
Friday
2/9/2018
Construction entrance removal
Monday
2/12/2018
Upper pedestrian bridge (LAW-02) installation
Thursday
2/15/2018
Paving*
Monday
2/19/2018
Planting
*Final asphalt when daytime temps stay above 45° F, towards
end of next week. Paving will be accessed from upstream Bachan Ct.