20018.04 / Lake Anne West· Next Wednesday 3/7/18 will be the final meeting and walk through for Lake Anne West· WSSI will post “No Mowing” signs Thursday 3/1/18· WSSI will closely monitor for any potential erosion on slope near construction entrance per resident request· WSSI to follow up with Waterview cluster on when vehicles can be driven down patho Waterview cluster to determine what equipment will be used for landscaping· TCOT will finish planting Thursday 3/1/18· TDS will replace concrete Thursday 3/1/18 weather permittingo @ Construction entrance§ All panels impacted by constructiono @ Junction of Bachan Ct. & trail§ 3 panels nearest trail§ Apron around drop inlet· TDS will complete trail shoulders and the following action items early next weeko @ Construction entrance§ Install bollard§ Cut 4’ holly stump closer to gradeo @ Junction of Bachan Ct. & trail§ Replace timber and river cobble at corner of trail§ Replace wooden post for guard railo Near lower trail crossing at bridge LAW-02§ Remove cable from Ash Log§ Replace timber in landscaping on south side of trail§ Re-grade minor erosion in last stream access point
Maintaining current contact information helps the board and its
committees reach owners and tenants with important board announcements
as well as during emergency events such as a water/gas main break or to
report storm damage to vehicles or other property. Each owner
and paying tenant should complete a separate form.
Non-resident owners should enter their address at the end of the
form. Note: You do NOT need to have a Google account in order
to update and submit the form.
!doctype>
February 28, 2018
February 22, 2018
20018.04 / Lake Anne West· WSSI to order and post “No Mowing” signs· Bollard to be installed by TDS to block vehicular traffic at LAW-01 bridge· Tentative schedule for completion by the end of February:
Friday 2/23/2018 Upper bridge (LAW-01) railings installed Thursday 2/22/2018 Plants delivered – planting to start next week Monday 2/26/2018 Paving starts* Wednesday 2/28/2018 Gravel shoulder installed along path*Final asphalt when daytime temps stay above 45° F and weather is dry, towardsBeginning of next week. Paving will be accessed from upstream at Bachan Ct.
February 15, 2018
Below are the meeting notes and the updated tentative completion schedule.TDS crews will not be working next Monday, President’s Day.20018.04 / Lake Anne West· WSSI to order and post “No Mowing” signs· Possible bollard installation discussed to inhibit vehicle traffic· Tentative schedule for completion by the end of February:
Thursday 2/15/2018 Lower bridge railings installed Thursday 2/15/2018 Construction entrance removal Friday 2/16/2018 Upper bridge footers set Tuesday 2/19/2018 Upper bridge deck set and railings started Thursday 2/22/2018 Paving* Thursday 2/22/2018 Plants arriving*Final asphalt when daytime temps stay above 45° F, towardsend of next week. Paving will be accessed from upstream Bachan Ct.Let us know if you have any questions.Daniel Misch |Ecosystem SpecialistISA Certified Arborist UT-4564AU
February 10, 2018
Lake Anne West 2/7/2018· Sub-surface flow is expected in low flow conditions until voids are filled· Bridge piers installed for downstream bridge (LAW-02) Tuesday 2/6/18· Oak tree at tributary 2 made safe with crown removal completed Tuesday 2/6/18· TDS punch list itemso Stabilize around upstream headwall STA 10+00.00 with A1 Rip Rapo Cut white pipe back to banko Install pipes under trail at Tributary 1· TCOT planting access with gator/cart· Tentative schedule for completion by the end of February:
Thursday 2/8/2018 Lower pedestrian bridge (LAW-02) installation Friday 2/9/2018 Construction entrance removal Monday 2/12/2018 Upper pedestrian bridge (LAW-02) installation Thursday 2/15/2018 Paving* Monday 2/19/2018 Planting*Final asphalt when daytime temps stay above 45° F, towardsend of next week. Paving will be accessed from upstream Bachan Ct.