Lake Anne West 2/7/2018· Sub-surface flow is expected in low flow conditions until voids are filled· Bridge piers installed for downstream bridge (LAW-02) Tuesday 2/6/18· Oak tree at tributary 2 made safe with crown removal completed Tuesday 2/6/18· TDS punch list itemso Stabilize around upstream headwall STA 10+00.00 with A1 Rip Rapo Cut white pipe back to banko Install pipes under trail at Tributary 1· TCOT planting access with gator/cart· Tentative schedule for completion by the end of February:
Thursday 2/8/2018 Lower pedestrian bridge (LAW-02) installation Friday 2/9/2018 Construction entrance removal Monday 2/12/2018 Upper pedestrian bridge (LAW-02) installation Thursday 2/15/2018 Paving* Monday 2/19/2018 Planting*Final asphalt when daytime temps stay above 45° F, towardsend of next week. Paving will be accessed from upstream Bachan Ct.