20018.04 / Lake Anne West· WSSI to order and post “No Mowing” signs· Bollard to be installed by TDS to block vehicular traffic at LAW-01 bridge· Tentative schedule for completion by the end of February:
Friday 2/23/2018 Upper bridge (LAW-01) railings installed Thursday 2/22/2018 Plants delivered – planting to start next week Monday 2/26/2018 Paving starts* Wednesday 2/28/2018 Gravel shoulder installed along path*Final asphalt when daytime temps stay above 45° F and weather is dry, towardsBeginning of next week. Paving will be accessed from upstream at Bachan Ct.